CXC Home | Search | Help | Image Use Policy | Latest Images | Privacy | Accessibility | Glossary | Q&A
Friday 11 March 2005 9.00am EST
During the last week Chandra completed the observing schedule as
planned.
An Aspect Camera dark current calibration was performed from the on-board loads on 10 March. The schedule of targets for the next week is shown below and includes an observation of SDSS J1411+1217 coordinated with ground observations. The source GRO J1655-40 was accepted on 10 March as a fast turn around (3 day) Target Of Opportunity and will result in a replan of the schedule. |
------------------------------------------
EGS-1 ACIS-I Mar 13 DLS J1356-1051 ACIS-I Mar 14 87GB 1243+2248 ACIS-S DLS J1356-1140 ACIS-I cl0328-2140 ACIS-I cl0318-0302 ACIS-I Mar 15 NGC7196 ACIS-S Radiation Belts EGS-1 ACIS-I Mar 16 SDSS J1411+1217 ACIS-S Mar 17 LCDCS 954 ACIS-S MACSJ1359.1-1929 ACIS-I cl1212+2733 ACIS-I G21.5-09 HRC-S Radiation Belts Mar 18 M86 ACIS-I Mar 19 EGS-2 ACIS-I
------------------------------------------
All spacecraft subsystems continued to support nominal operations.
Return to Status Reports