Friday 22 February 2008 9.00am EST
During the last week the observing schedule was replanned to include
an 85 Ks observation of 4U 1812-12 that was accepted as a fast
turn-around Target Of Opportunity (TOO) on Feb 15. Loads were
replanned and uplinked on Feb 17 for an observation on Feb 18.
Observations of UGC 4203, RX J1131-1231, Carina South Pillars, IGR J18485-0047, IGR J18308-1232 and XTE J1810-197 were impacted by the TOO and will be rescheduled in a later load.
A Chandra image release was issued on Feb 21 of the pulsar in Kes 75. The Chandra data combined with RXTE timing measurements indicate behavior that suggests the object may fill a gap between that of pulsars and magnetars. For futher details see: http://chandra.harvard.edu/photo/2008/kes75/ The schedule of targets for the next week is shown below. |
------------------------------------------
Radiation Belts Feb 26 Carina South Pilla ACIS-I NGC 3957 ACIS-S BR1202-0725 ACIS-S Feb 27 IGR J18325-0756 ACIS-S IGR J19443+2117 ACIS-I IGR J19267+1325 ACIS-I AX 1845.0-0433 ACIS-S SDSS J1421+3433 ACIS-S Feb 28 1910 ACIS-S 2000 ACIS-S NGC 4308 ACIS-S 1849+670 ACIS-S Radiation Belts Carina South Pillars ACIS-I Feb 29 cl0237-5224 ACIS-I AX J190818+0745 ACIS-S 2XMMp J123719.3+11 ACIS-S 1938 ACIS-S Mar 1 1871 ACIS-S AX J184652-0240 ACIS-S AX J184400-0355 ACIS-S RXCJ0220.9-3829 ACIS-I Carina South Pillars ACIS-I AX J185608+0218 ACIS-S Mar 2 J1928+1746 ACIS-I Radiation Belts H1743-322 ACIS-S/HETG Abell 2220 ACIS-S Mar 3 NGC4151 HRC-I
------------------------------------------
All spacecraft subsystems continued to support nominal operations.