Operations CXO Status Report

Friday 7 December 2007 9.00am EST

During the last week Chandra completed the observing schedule as planned.

A real-time procedure was executed on Dec 4 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer.

The schedule of targets for the next week is shown below and includes observations of NCG 1023 coordinated with HST and AEGIS coordinated with Spitzer.

------------------------------------------
Draco                  ACIS-S       Dec 9
3C332                  ACIS-S
3C315                  ACIS-S       Dec 10
SDSS J133701.39-02     ACIS-S
Radiation Belts
AEGIS-1                ACIS-I
3C 186                 ACIS-S       Dec 11
NGC2563-P2             ACIS-I
SDSS J074610.50+23     ACIS-S       Dec 12
NGC1023                ACIS-S
Radiation Belts
AEGIS-1                ACIS-I       Dec 13
074345.47+480813.5     ACIS-S
NGC2563-P5             ACIS-I       Dec 14
V1118 Ori              ACIS-S
SN 2006gy              ACIS-S
Draco                  ACIS-S       Dec 15
Radiation Belts
AEGIS-1                ACIS-I       Dec 16
3C197.1                ACIS-S

------------------------------------------

All spacecraft subsystems continued to support nominal operations.

Return to Status Reports