Operations CXO Status Report

Friday 16 June 2006 11.00am EDT

During the last week Chandra completed the observing schedule as planned.

Power to the OCC was disrupted for 15.5 hours on 13 Jun due to planned construction activity in the building. Power to all operational required operations equipment was provided by the emergency gas generator for the outage and there was no impact to operations.

Preparations are complete for the Cycle 8 Peer Review to be held in Boston next week.

The schedule of targets for next week is shown below and includes an observation of GX340+0 coordinated with the VLA and RXTE.

------------------------------------------
Radiation Belts                      Jun 19
HD93250                 ACIS-S/HETG
RXC J1110.5+2842        ACIS-S       Jun 20
P1                      ACIS-I
P6                      ACIS-I
P10                     ACIS-I
P13                     ACIS-I
Dwingeloo 1             ACIS-I
SDSS J0121+1448         ACIS-S       Jun 21
GX 340+0                ACIS-S/HETG
Radiation Belts
HD93250                 ACIS-S/HETG  Jun 22
PSRJ1617-5055           ACIS-I
HD93250                 ACIS-S/HETG  Jun 23
SC1604+4323             ACIS-I
SDSSJ0132-0952          ACIS-S       Jun 24
Radiation Belts
SC1604+4323             ACIS-I
Q0948+4323              ACIS-S       Jun 25
NGC 3432                ACIS-S
NGC 3413                ACIS-S
SDSS J100711.82+05      ACIS-S
Q1225+0035              ACIS-S
HD 150798               HRC-I
Q2237+0305              ACIS-S

------------------------------------------

All spacecraft subsystems continued to support nominal operations.